Bhama Askhed Project

Bhama Askhed Project
Order
3
Display format
Grid
Other Details

Bhama Askhed Water Supply Scheme for the Eastern part of Pune City:

The scheme is designed for water supply of 200 MLD. It will cover 58 sq.km area of the eastern part of Pune city along the Nagar road for projected population of 14.50 lac up to 2041.

This project is sanctioned under JNNURM scheme of Govt. of India vide sanction letter no. K14012/2(123)/2006-NURM-III dated 5th July 2013 amounting to Rs. 380.16 Crores. The funding from details are as follows:

SourcePercentageAmount
Govt. of India50%Rs. 190.08 Cr.
Govt. of Maharashtra20%Rs. 76.03 Cr.
PMC30%Rs. 114.051 Cr.
Total100%Rs. 380.16 Cr.

We have received two installments from GOI & GOM as mentioned below. The proposal for release of the 3rd installment has been sent to the Govt. of India.

S.No.SourceAmount
1Govt. of India (GOI)Rs. 76.03 Cr
2Govt. of Maharashtra (GOM)Rs. 30.40 Cr.
TotalRs. 106.43 Cr.

Bhama Askhed Water Supply Scheme is divided in 6 Package as below:

Package No.NameEstimated Cost
1Construction of Jackwell & Pump HouseRs. 54.89 Cr.
2Providing & Laying Raw Water M.S. PipelineRs. 127.44 Cr.
3Construction of Water Treatment Plant at KuruliRs. 58.68 Cr.
4Providing & Laying Pure Water M.S. PipelineRs. 70.77 Cr.
5Providing & Laying Feeder Main PipelineRs. 55.08 Cr.
6Construction of 7 Nos. of ESR of 2 ML Capacity EachRs. 12.69 Cr.

The up to date expenditure is Rs. 172.00 Cr. The work was stopped by local MLA & farmers for their various demands from Oct 2015. These demands were concerned with the Govt. of Maharashtra. After the meeting with Hon. Chief Minister (Govt. of Maharashtra) on 13 / 05 / 2016 and continuous follow up with the State Govt Departments and officials, most of the demands were fulfilled and work was restarted from June 2016. Work on the raw water rising pipeline (8 KM) from Bhama Askhed Dam to BPT at Bhamboli is still stopped by Local MLA.

Our target completion date is 31 July, 2017 and all the contractors are notified of the same. Weekly project review meetings are held with the contractors to ensure proposed timelines are met.

Project Status
Completed